Transnet Corridor Studies
Client : Transnet Projects
Location : Johannesburg,
Involvement : Rail Network Capacity Studies
Value : R8 million
Purpose : Feasibility Study to determine current installed infrastructure capacity and to develop capacity increase proposals to satisfy next 30 years
Duration : September 2006 – December 2007
During 2006, R&H was contracted by the Hatch, Mott MacDonald and Guba “HMG” Joint Venture to conduct a pre-feasibility study on the entire Transnet Freight Rail network. The aim of this study is to determine the current installed rail infrastructure network capacity and to develop a 30 year investment strategy and plans that will be able to cater for future South African transportation needs. The output of the study is a “30 Year National Rail Infrastructure Plan”.
For more information, download pdf project sheet (to save this file, right click on the link, and choose the 'save as' option).